What happened on site Phase 1

Another project milestone was reached this week with the opening of the new pedestrian and cyclist footbridge over the A9. The new bridge, which has been named “Inveralmond Skywalk” by a pupil at Ruthvenfield Primary School, links Inveralmond Industrial Estate with Auld Bond Road as well as linking the Town Lade path.

Elsewhere on site, landscaping works including tree and shrub planting are ongoing at Ruthvenfield Roundabout and the Town Lade path.

Street lighting works are ongoing at various locations throughout site.

Kerbing and road construction works are taking place on the Loop Road off the A85 Crieff Road and the new West Connector junction with the A85.