Project Update – September 25th 2023

25th September, 2023
CTLR Updates

A9 update

Earthworks continuing to form park and cycle route from east roundabout.


Earthworks to form drainage pond, juts south of A9 overbridge.


Setting out of new fence along Redgorton access road.


Removal of old fence along Redgorton access road.


Installation of sign plates onto sign posts previously installed along northbound carriageway.


Tay Crossing Update

Works have been continuing on the construction of the traveller system and temporary props which will be used to construct the Tay Crossing concrete deck on the east pier side.


Works have been continuing on the construction of the traveller system and temporary props which will be used to construct the Tay Crossing concrete deck on the west pier side.


Link Road Update

Earthworks underway for backfill of embankment of the Green Bridge.


Surfacing non-motorised footpath from A93 roundabout towards Green Bridge.