Project Update - May 8 2023
A9 update
Completion of applying and rolling cement-bound granular material (a granular material or soil, mixed with cement, which is used as a subbase for the paving).
![](/files/_medium/Project-Update-May-8-2023-1.jpg)
![](/files/_medium/Project-Update-May-8-2023-2.jpg)
![](/files/_medium/Project-Update-May-8-2023-3.jpg)
BT operative pulling cables through ducts.
![](/files/Project-Update-May-8-2023-4.png)
![](/files/Project-Update-May-8-2023-5.png)
Construction of access to deck of A9 overbridge for concrete pour of diaphragms.
![](/files/_medium/18367/Project-Update-May-8-2023-6.jpg)
Installation of drainage under southbound carriageway.
![](/files/Project-Update-May-8-2023-8.png)
![](/files/Project-Update-May-8-2023-7.png)
Tay Crossing Update
Preparing for east pier pile cap concrete pour. Laying spacer blocks down on concrete blinding for steel reinforcement cage to be constructed upon.
![](/files/_medium/Project-Update-May-8-2023-9.jpg)
![](/files/_medium/Project-Update-May-8-2023-10.jpg)
Completion of pile installation on west pier and pile rig moved over to east side.
![](/files/_medium/Project-Update-May-8-2023-12.jpg)
![](/files/_medium/Project-Update-May-8-2023-11.jpg)
Link Road Update
Drainage installation on west bound carriageway, near A93 roundabout.
![](/files/_medium/Project-Update-May-8-2023-13.jpg)
Laying and rolling of type 1 subbase from Tay crossing heading east, ready for CBGM to be installed.
![](/files/_medium/Project-Update-May-8-2023-15.jpg)
![](/files/_medium/Project-Update-May-8-2023-14.jpg)
Pouring of concrete kerbs at Stormontfield roundabout.
![](/files/_medium/Project-Update-May-8-2023-17.jpg)
![](/files/_medium/Project-Update-May-8-2023-16.jpg)