Project Update – May 15 2023

15th May, 2023
CTLR Updates

A9 update

Cement-bound granular material (a granular material or soil, mixed with cement, which is used as a subbase for the paving) being applied and rolled on the A9 northbound carriageway.

Laying tarmac on northbound carriageway

Tay Crossing Update

Preparing for east pier pile cap concrete pour.

Link Road Update

Drainage installation on eastbound line between Stormontfield and A93.

Continuing pouring of concrete kerbs on Stormontfield roundabout