Project Update – March 30 2023
A9 update
Erecting formwork for west wingwalls of A9 overbridge
![](/files/Project-Update-–-March-30-2023-2.jpg)
East abutment stem wall poured for A9 overbridge
![](/files/Project-Update-–-March-30-2023-1.png)
Placing and compacting stone to formation level along mainline road
![](/files/Project-Update-–-March-30-2023-5.jpg)
![](/files/Project-Update-–-March-30-2023-4.jpg)
Tay Crossing Update
Excavation of east pier cofferdam.
![](/files/Project-Update-–-March-30-2023-6.jpg)
![](/files/Project-Update-–-March-30-2023-7.jpg)
Concreting west pier pile 20.
![](/files/Project-Update-–-March-30-2023-8.jpg)
Link Road Update
Installation of manhole east of Stromontfield roundabout.
![](/files/Project-Update-–-March-30-2023-9.jpg)
Installation of Scottish water main SWP014
![](/files/Project-Update-–-March-30-2023-10.jpg)
![](/files/Project-Update-–-March-30-2023-11.jpg)
Completed installation of beams of Green Bridge
![](/files/Project-Update-–-March-30-2023-13.jpg)
![](/files/Project-Update-–-March-30-2023-12.jpg)
![](/files/Project-Update-–-March-30-2023-14.jpg)