Project Update | March 28th 2024

28th March, 2024
General News
CTLR Updates

"The turbulent winter continued into March with heavy rainfall and cold temperatures which has proved challenging for the entire project team. Despite this, works have progressed well and we are particulalry pleased to see the first four deck segments complete on Destiny Bridge." - Derek Walsh, Contract Manager for BAMUK & I

New Kingsway (Link Road)

The New Kingsway works have progressed well with traffic signs, street lighting, vehicle safety barriers, and landscaping nearing completion between the A93 and A94 roundabouts.

The open section of the New Kingsway between Stormontfield roundabout and the A93 roundabout has been well-received by the local community and offers a glimpse of what the completed road will look like. This section is facilitating local upgrade works to the existing Stormontfield Road which has progressed well.

The majority of the surfacing works have been completed in March with remaining works (wearing course, signage and verge finishes) anticipated to be completed during the next period.

Work on the Green Bridge at Highfield has also progressed well in the period; the remaining works including landscaping, fencing and pathways are scheduled for completion in the next period, facilitating the connection between the new road to Highfield Plantation for active travel users and wildlife.

Access paths leading up to the bridge are scheduled for completion in late spring 2024.

Destiny Bridge

The west abutment stem wall located immediately west of the Highland Railway line has progressed well with the second pour of three now complete. With the east abutment foundation completed, the abutment (end support) construction will now commence.

All four Balanced Cantilever Form Travellers are now in position on the structure hammerheads.

The construction of the initial Form Traveller deck segments of reinforced steel, high-strength concrete, and post-tensioning cables is now underway and during March the first four segments were complete.

A careful construction sequence will ensure that a segment will be constructed on either side of each pier to maintain a perfect balance. The bridge is currently forecast to be completed in 2024.

A9

The new A9 alignment to the west well-established and working well for drivers, and in addition to this, ancillary works such as bus-bays, footpaths, and accommodation works have now been completed.

The focus now remains on the next phase of the works. The earthworks and drainage along the old A9 route are well underway and the drainage for the new Park & Choose area are now completed.

The A9 Overbridge superstructure has advanced well, with the finishing works (kerbing, ducting and hard landscaping) underway. Surfacing works on the adjacent roundabouts has also commenced in the period.

Opening of the existing cycle path for use by both cyclist and pedestrian users has allowed for a new diversion route, enabling works to progress for the Denmarkfield Access Portal. Piling works for the portal has progressed well, with an anticipated completion date in the next few weeks.

Keep Up To Date: Sign up to our monthly newsletter for Project News and Community Benefit Updates >