Project Update – March 1 2023
A9 update
Grader grading material along A9 mainline.
![](/files/March-1-2023-1.jpg)
![](/files/March-1-2023-2.jpg)
4-way BT and communications ducting installed at southbound sliporoad and through Bertha cut.
![](/files/March-1-2023-3.jpg)
Tay Crossing Update
Piling operations continue on both sides of the Tay Crossing. West pier columns all complete. East pier concrete pour for pile 21, with 4 piles left to completion.
![](/files/March-1-2023-6.jpg)
![](/files/March-1-2023-5.jpg)
West abutment stem wall formwork ongoing.
![](/files/March-1-2023-7.jpg)
Link Road Update
Waterproof paint applied to green bridge abutments, ready for backfill.
![](/files/March-1-2023-8.jpg)
Drainage squads installing 150mmØ pipe between manholes PKC-4/8 – PKC-4/9.
![](/files/March-1-2023-9.png)
![](/files/March-1-2023-10.jpg)
Drainage squad installing manhole PKC-5/73.
![](/files/March-1-2023-11.jpg)
Grading stone up to subformation level of road between A93-A94.
![](/files/March-1-2023-12.jpg)
Drainage squads installing 450mmØ pipe between manholes PKC-5/37 – PKC-5/36.
![](/files/March-1-2023-13.jpg)