Project Update - June 5 2023

5th June, 2023
CTLR Updates

A9 update

Drainage Installation through Bertha cut.

A9 overbridge deck concrete pour.

Construction of traffic signs foundations

Tay Crossing Update

Preparation for east pier pile cap pour. Steel bar fixed together to construct reinforcement cage.

Piling rig moved from west pier over to begin west abutment piling.

Link Road Update

BT and power duct installation on the west bound side, near the Green Bridge.

Duct installation at A93 roundabout.

A94 tarmac complete on east side and preparation for traffic change over in order to start construction of west side of roundabout.

Drainage manhole installation as well as grading edge of road for kerb construction.

Laying and compacting type 1 graded stone along link road from A94 to Highfield roundabout, ready for CBGM.

After allowing CBGM to set, tarmac was applied to the link road from the bridge, heading east towards Stormontfield.