Project Update – July 3 2023
A9 update
Earthworks for southbound slip way tie in from roundabout.
![](/files/_medium/Project-Update-July-3-2023-2.jpg)
![](/files/_medium/Project-Update-July-3-2023-1.jpg)
![](/files/_medium/Project-Update-July-3-2023-3.jpg)
Continuing earthworks for southern tie in of the new southbound carriageway.
![](/files/_medium/Project-Update-July-3-2023-4.jpg)
Installation of drainage at north tie in.
![](/files/_medium/Project-Update-July-3-2023-5.jpg)
Continue excavation of material for construction of south pond.
![](/files/_medium/Project-Update-July-3-2023-6.jpg)
Tay Crossing Update
Installation of formwork in preparation for east pier stem concrete pour. Bracing for shutters installed.
![](/files/_medium/Project-Update-July-3-2023-8.jpg)
![](/files/_medium/Project-Update-July-3-2023-7.jpg)
Completion of excavating down to formation level and blinding area in preparation for west pier pile cap construction. Blinding is a base layer of concrete to provide a level, stable platform atop which structural concrete can be constructed.
![](/files/_medium/Project-Update-July-3-2023-10.jpg)
![](/files/_medium/Project-Update-July-3-2023-9.jpg)
![](/files/_medium/Project-Update-July-3-2023-12.jpg)
![](/files/_medium/Project-Update-July-3-2023-11.jpg)
Link Road Update
Surfacing of the eastern side of new Stormontfield roundabout. Traffic to be running on contraflow next week while construction of western side commences.
![](/files/_medium/Project-Update-July-3-2023-14.jpg)
![](/files/_medium/Project-Update-July-3-2023-13.jpg)
Services works at the A94 continued before new allignement construction can commence.
![](/files/_medium/Project-Update-July-3-2023-17.jpg)
![](/files/_medium/Project-Update-July-3-2023-16.jpg)
![](/files/_medium/Project-Update-July-3-2023-15.jpg)
![](/files/_medium/Project-Update-July-3-2023-18.jpg)