Project Update – July 17 2023

17th July, 2023
CTLR Updates

A9 update

Earthworks around eastern roundabout of A9 overbridge.

Base and binder course (bottom and middle layer) of tarmac laid and rolled for southern tie of southbound carriageway.

Installation of crash barriers in central reservation.

Concrete pour for parapets for A9 overbridge.

Tay Crossing Update

Installation of steel formwork/shuttering for west pier pile cap concrete pour.

Continued construction of steel reinforcement for second pour of east pier stem.

Installation of piles for west abutment.

Set up of balanced cantilever system on east side in preparation of bridge deck installation.

Link Road Update

Construction of western side of Stormontfield roundabout and approach road.

Construction of west side of new A94 allignment and roundabout.

Construction of cycle/footpaths between Stormontfield roundabout and A93.

Installation of drainage for Stormontfield roundabout.