Project Update – July 10 2023
A9 update
Completion of earthworks for southbound slip way tie in from roundabout.
![](/files/_medium/Project-Update-–-July-10-2023-1.jpg)
Completion of earthworks for southern tie in of the new southbound carriageway and commencing laying cement-bound granular material. This material is used as a sub base for the surfacing for the road.
![](/files/_medium/Project-Update-–-July-10-2023-3.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-2.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-4.jpg)
Service diversion works carried out at Tay crossing underpass location.
![](/files/_medium/Project-Update-–-July-10-2023-5.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-6.jpg)
Tay Crossing Update
First pour for east pier stem.
![](/files/_medium/Project-Update-–-July-10-2023-7.jpg)
Stripping of formwork for east pier stem.
![](/files/_medium/Project-Update-–-July-10-2023-9.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-8.jpg)
Construction of steel reinforcement for west pier pile cap concrete pour.
![](/files/_medium/Project-Update-–-July-10-2023-11.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-10.jpg)
Construction of steel reinforcement for second pour of east pier stem.
![](/files/_medium/Project-Update-–-July-10-2023-13.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-12.jpg)
Link Road Update
Laying of binder course (middle layer) of Tarmac from A93 roundabout towards green bridge.
![](/files/_medium/Project-Update-–-July-10-2023-14.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-15.jpg)
Construction of west side of new A94 allignment and roundabout.
![](/files/_medium/Project-Update-–-July-10-2023-16.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-18.jpg)
![](/files/_medium/Project-Update-–-July-10-2023-17.jpg)