Project Update – April 17 2023
A9 update
Installing steel reinforcement and concrete formwork for SE and NE abutment wingwalls of A9 overbridge.
![](/files/Project-Update-–-April-17-2023-1.png)
![](/files/Project-Update-–-April-17-2023-2.png)
Cement-bound granular material (a granular material or soil, mixed with cement, which is used as a subbase for the paving) being applied and rolled on the A9 southbound carriageway. A roller is then used to compact the material to ensure it achieves required strength.
![](/files/Project-Update-–-April-17-2023-4.png)
![](/files/Project-Update-–-April-17-2023-3.png)
Northbound carriageway drainage installation
![](/files/Project-Update-–-April-17-2023-5.png)
Tay Crossing Update
Commencing excavation of material of east side pier down to formation level of east pier pile cap.
![](/files/_medium/Project-Update-–-April-17-2023-6.jpg)
![](/files/_medium/Project-Update-–-April-17-2023-8.jpg)
![](/files/_medium/Project-Update-–-April-17-2023-7.jpg)
Continued pile installation on west pier.
![](/files/Project-Update-–-April-17-2023-9.png)
Link Road Update
Drainage installation on westbound line, between Stormontfield and A93.
![](/files/_medium/Project-Update-–-April-17-2023-11.jpg)
![](/files/_medium/Project-Update-–-April-17-2023-10.jpg)
Placing and compacting type 1 graded stone subbase for link road from Tay crossing heading East. Type 1 graded stone is a 40mm graded to dust material that is laid and compacted to form a level stable construction layer as a platform for the road surfacing to be laid on.
![](/files/_medium/Project-Update-–-April-17-2023-12.jpg)
Commenced pouring of insitu kerbs for Stormontfield Roundabout
![](/files/_medium/Project-Update-–-April-17-2023-14.jpg)