What’s happening on site 28-04-2017

This week on site has seen the completion of the pilling operations on the west abutment of structure S01 (road bridge over the A9), with work due to commence next week on the east abutment.

Works are well underway installing kerbing to the area adjacent to the Crematorium Drive off the Crieff Road in preparation for surfacing to be laid in mid-May.

Works to construct the west section of S05 culvert under the A9 are progressing well, with formwork and reinforcement currently being installed.

The last remaining wall sections of S04 culvert are prepared ready for the final wall concrete pour next week, with preparations underway for construction of the roof slab.

Pilling operations have commenced to install the foundations for structure S02 (road bridge road over the River Almond). A viewing platform has been installed next to this structure, off cycle route NCR77, to allow members of the public to follow the construction of the new bridge.