This week a start has been made on building up the new embankments on the west side of the A9 with lightweight fill.
The town lade is now running in its new temporary position which allows installation of the band drains to be completed.
Work has commenced on installing the base layer for S04 culvert. Once complete, this culvert will carry the town lade and a pedestrian footpath under the new road.
Work has been ongoing to install a concrete pipe culvert to the north of the River Almond.
Weekend tree felling works around the Crematorium area has also continued with tree felling taking place to the east of the A9 during the week.