What’s happening on site 25 08 2017

The first concrete pour to form the bridge deck of structure S01 bridge over the A9 took place this week. 100 cubic metres of concrete was pumped on to the bridge deck to form the middle two thirds of the reinforced concrete slab. Work is now underway to install shuttering in preparation for the two remaining concrete pour.

Kerbing, drainage and utility works are continuing at the new junction around Perth Crematorium.

Works have commenced to form the new northbound merge slip road on to the A9.

Preparations for the arrival of the steel beams for structure S02 bridge over the River Almond have been taken place. A beam lay down area has been formed and works to the pier and bridge abutments are progressing.

Works to the Crematorium overflow parking are nearing completion and the new Crematorium wall construction is progressing.