What’s happening on site 24-11-2017

Work to install the permanent traffic signals at the A85 west junction has been ongoing this week. This is planned to be completed by the middle of next week at which point the temporary signals will be removed.

Construction of the footpaths and cycle paths around the new Crematorium area has been ongoing, with surfacing works taking place to sections of these this week.

Road surfacing works have also been taking place on the section between the A85 Crieff Road and the new Crematorium entrance.

Lightweight fill is continuing to be installed to the west side of Structure S01, bridge over the A9, with steel reinforcement and shuttering works taking place on the east side.

Reinforcement and shuttering works are ongoing at Structure S02, bridge over the River Almond, with works also being carried out on the bridge bearings.

Kerbing works have been continuing to the section of road between Ruthvenfield Road and Bertha Park.