What’s happening on site 23-03-2018

Waterproofing works to the concrete deck of the new bridge over the River Almond have been taking place this week.

Piling works were completed this week for structure S03, the new footbridge over the A9.

Excavation works are continuing for the new lade pedestrian culvert.

Surfacing works have been continuing to Ruthvenfield Roundabout with base and binder courses being laid this week.

Construction of the new combined footway and cycle way is continuing through the Bertha Park area and around the new Crematorium entrance.

Drainage works are continuing on the west connector road and to the new Northbound merge slip road on to the A9.