What’s happening on site 22-09-2017

The final beam lifts for Structure S02 were completed this week, along with the installation of the formwork and temporary scaffolding to allow works to commence on the deck.

The first road layer (type 1 sub base) has been laid this week on the section of road by the new Crematorium entrance towards the A9. On completion of this, works will then start on kerbing this section.

The construction of the new Crematorium wall is nearing completion with the new stone pillars and Perth Crematorium signs being installed.

Earthworks are continuing forming the new southbound diverge slip road and the new northbound merge slip road to the A9.

The final concrete pour to form the deck of Structure S01 bridge over the A9 has been completed, along with section of the east wing walls