What’s happening on site 20-10-2017

Work has continued this week on the wing walls for structure S01 bridge over the A9. The east side wing walls are now complete and the shuttering removed. Work is ongoing on the west side.

Installation of steel reinforcement is continuing for the deck of structure S02, bridge over the River Almond.

The preparation works to the section of new road in front of the new Crematorium entrance is now completed ready for surfacing to be carried out next week.

The new Crieff Road junction has seen surfacing works take place to form what will become a new left turn lane from the existing Crieff Road on to the new road.

Earthworks fill is ongoing to the areas immediately east and west of the A9.

Preparation works to the new Bertha Park roundabout are nearing completion with surfacing works also planned to this area next week.