What’s happening on site 20-04-2018

Surfacing of the footpaths leading to the Crematorium has been completed this week, as has the majority of the road in this area.

Works are continuing constructing the parapet support walls on each approach to structure S01, the new road bridge over the A9.

Drainage works have been ongoing to the new A9 southbound slip road.

Works have commenced constructing the new SUDS pond to the west of Auld Bond Road.

Works are continuing installing the steel reinforcement for the foundations of structure S03, new footbridge over the A9.

The construction of the new pedestrian underpass alongside the Town Lade is progressing, with backfill around the structure ongoing this week.