What’s happening on site 19-01-2018

Works have commenced this week on the construction of the new Ruthvenfield Roundabout. This will link Ruthvenfield Road in to the new road towards the A9 and Crieff Road to the east, and Bertha Park to the west.

Installation of reinforcement bar and formwork has been continuing on Structure S01 east and west abutments.

Works have commenced on the formwork and reinforcement bars for the copes on Structure S02.

Surfacing to the footpaths around the new Crematorium access has taken place this week, with works also ongoing to construct the final sections of road and wall in this area.

Work as commenced on upgrading the pedestrian footpath that runs down the east of the Crematorium.