What’s happening on site 18 08 2017

Works are progressing well with the construction of the new Perth Crematorium wall and overflow parking areas.

Steelwork has been installed for the reinforced concrete deck of structure S01, new bridge over the A9.

Β 

The Town Lade has been diverted and is running in its new permanent position with structure S04 that carries the lade now backfilled over.

Works are ongoing to install the drainage for the proposed roundabout on Ruthvenfield Road.

The first major concrete pour to bridge S02 over the River Almond has been completed this week with around 110 cubic metres of concrete poured to form the central pier.