What’s happening on site 17-08-2018

A milestone in the project was reached this week with the installation of the new footbridge over the A9. The footbridge ramps were lifted in to place using a 300t crane during the day on Monday and Tuesday, with the main truss craned in to place overnight on the Wednesday.

With the traffic management in place on the A9, works to form the revetment under structure S01 (A9 overbridge) was able to take place as well as road marking, drainage and signing works on the A9.

Works to surface the footpaths on the west connector road and around structure S01 have been ongoing this week, as has footpath works to the new lade side path and pedestrian underpass.

Work is continuing on the new southbound merge slip road with earthworks and drainage works ongoing.