Works this week include:

Lade culvert progressing with Re-bar being installed and handled with the new heavy crane.

Earthworks for the new embankment taking shape @ Ruthvenfield Link

More instrumentation being added to monitor site conditions

Using resources on-site well underway @ Bertha Park.

New Drainage pipe at the Crematorium

Earthworks East of A9 progressing.