Pilling works for the new footbridge over the A9 have commenced this week. A total of 22 piles will be installed to support the new bridge.

Kerbing and the installation of type 1 sub base has been ongoing at Ruthvenfield Roundabout this week, with the first of the road surfacing material laid to the roundabout on Friday.

Drainage installation works and the construction of the new shared use footway / cycleway towards the new Crematorium entrance is also on going.

Excavation works for the new pedestrian underpass along the lade is continuing with filling also continuing to the new northbound merge slip road on to the A9.

Drainage installation works are ongoing on the west connector road.