What’s happening on site 16-02-2018

Works have started on forming the new road surface at Ruthvenfield Roundabout this week. Sub-base has been installed to a large proportion of the roundabout and kerbing works have commenced.

Earthworks fill is nearing completion forming the new northbound merge slip road to the A9.

Drainage installation and earthworks are continuing on the main line by the Crematorium.

The last of the deck copes have been poured on structure S02 (bridge over the River Almond).

ย 

Landscaping works have been taking placeย in the Bertha Park area.

Backfilling to structure S01 (bridge over the A9) has been ongoing, with the earthworks now approaching the level of the new bridge.