What’s happening on site 15-12-2017

Some works have been restricted this week due to the cold temperatures, however work has commenced on the final section of the new Crematorium wall.

Kerbing work has been taking place around the new Crematorium access.

 

Earthworks fill has been ongoing to the area around the Southbound Diverge, S01 west and to the new west connector road.

 

Installation of formwork and steel reinforcement has been ongoing on the north side of Structure S02, bridge over the River Almond.