What’s happening on site 14-09-2018

This week saw the opening of the west connector road and the southbound merge slip road on to the A9.

Sub-baseΒ is being installed on the new Ruthvenfield Link Road.

Base course is being installed on the new southbound merge slip road on to the A9.

Work has started installing the CCTV poles.

Welding works are still ongoing to the new footbridge over the A9 with civils work taking place to form the approach paths to the new bridge.

Landscaping works are ongoing throughout the site.