What’s happening on site 13-10-2017

Following completion of the steel reinforcement installation of Structure S01 east wingwalls last week, the first of the two concrete pours to form the wingwalls took place this week. Work has also started on forming the wingwalls on the west side of the structure.

Installation of the deck reinforcement for Structure S02 bridge over the River Almond, is ongoing.

Work is progressing well on the construction of the new A85 Crieff Road west junction and the section of road in front of the new Crematorium entrance. Surfacing work is due to take place in these areas next week.

Earthworks fill is continuing, forming the new Southbound diverge slip road from the A9 and the area around the new roundabout on Ruthvenfield Road.

Work is progressing on the installation of slope drainage in the Bertha Park area, with works also ongoing forming the new combined footway / cycleway in this area.