What’s happening on site 13-07-2018

Works are continuing constructing the SUDS pond by the Crematorium. The pond bed has been completed this week with work starting on forming the footpath that will link to Allison Crescent and Pullar Terrace.

Road surfacing works have been completed across S01 (new bridge over the A9), the West Connector road and the new northbound merge slip road on to the A9.

Works have also commenced on forming the new lade side footpath.

Kerbing works have started on the Ruthvenfield Link secion, between the A9 and Ruthvenfield roundabout.

The steelwork for the west foundations of the new pedestrian footbridge over the A9 has been installed this week in preparation for pouring the concrete here next week.

General street lighting, utility ducting and landscaping works have been ongoing throughout the site.