What’s happening on site 12-10-2018

Works to surface the new lade side footpath and approaches to the new footbridge over the A9 were completed this week. Landscaping and street lighting works are now taking place here.

Kerbing and surfacing works have been taking place on the new access loop road off the A85 Crieff Road.

Works to complete the new southbound merge slip road on to the A9 have been ongoing this week with the focus now on completing the tie in section to the A9. Landscaping and drainage works have also been ongoing in this area.

Kerbing and footpath works are taking place on the Ruthvenfield Link section.