What’s happening on site 12-05-2017

The first roof slab pour of culvert S04 has taken place this week

The walls and roof slab of culvert S05 under the existing A9 have been completed this week and work has also progressed on forming the culvert inlet.

Pilling works are progressing on structure S01 bridge over the A9, and structure S02 bridge over the River Almond.

 

The first major section of road surfacing has been laid this week to the new section of road at its junction with the A85 Crieff Road.

Elsewhere, earthworks fill is continuing in various locations, drainage is being installed around the Ruthvenfield Road area and various public utility diversion works are taking place.