What’s happening on site 12-01-2018

Works have resumed this week following the Christmas break.

Earthworks have resumed to form the new west connector road between the existing A85 and Structure S01 bridge over the A9.

Work has also resumed forming the new southbound diverge slip road off the A9.

Further concrete pours have taken place this week to form the deck section of structure S02 bridge over the River Almond as well as the parapet support slabs on Structure S01 and infilling of the old lade culvert which is now redundant.