What’s happening on site 11-05-2018

Works to surface the southbound diverge have commenced this week. The base and binder road surface courses have been laid with the final course due to be laid next week.

Works have continued on the A85 east junction tie in with kerbing and footpath construction works ongoing here.

The installation of the acoustic fence has commenced south of the new Crematorium entrance with works also ongoing in this area constructing the SUDS pond.

Construction of the new footbridge over the A9 is progressing with the foundation bases poured this week.

Kerbing works are continuing on the west connector road.

 

Works are ongoing upgrading a section of cycle route NCR77 alongside the River Almond.