What’s happening on site 10-08-2018

Works have been ongoing constructing the new pedestrian footbridge over the A9, with the support columns for the ramps installed this week.

Works have been continuing on the SUDS pond by the Crematorium. The footpath linking the new road with Pullar Terrace and Allison Crescent has been surfaced this week.

Construction of the new southbound slip road on to the A9 has also been ongoing. Drainage has been installed and work has commenced on the road construction.

Elsewhere on site, footpath preparation works have been taking place on the west connector road and the link road between the A9 and Ruthvenfield roundabout. Slope soiling and landscape preparation works have been ongoing throughout the site.