What’s happening on site 09-02-2018

Works have been continuing on the construction of Ruthvenfield Roundabout this week. Drainage installation and bulk earthworks have been ongoing, as well as public utility works.

Surfacing works have taken place at the new road tie in with Crieff Road, as well as footways works in the same area. Drainage works have been ongoing in this area.

Landscaping works have commenced this week around the Crematorium area.

Earthworks are continuing, forming the new northbound merge slip road.

A further concrete pour to form the copes for Structures S02 (bridge over the River Almond) has taken place this week.