What’s happening on site 08-12-2017

Access to the Crematorium has been switched this week with traffic now using part of the newly constructed road and new Crematorium entrance. Work has now started on the remaining section of the Crematorium Wall.

Earthworks fill has been ongoing to the Southbound Diverge and to the area east of Structure S01, bridge over the A9.

 

Works have been continuing on the new West Connector Road.

The first section of deck has been poured on Structure S02, bridge over the River Almond.

 

Kerbing and footway preparation works have been ongoing in the Bertha Park area.