What’s happening on site 07-09-2018

Works have continued constructing the new parking bays on the loop road off the A85 Crieff Road.

Work has been completed installing the new CCTV camera bases.

Type 1 is currently being installed on the new southbound merge slip road on to the A9.

Signing and barrier installation has been ongoing on the west connector link road and the new A9 northbound merge slip.

Welding works are still ongoing to the new footbridge over the A9 with civils work taking place to form the approach paths to the new bridge.

Landscaping works are ongoing throughout the site.