What’s happening on site 04-05-2018

Surfacing works to tie in the new A85 Crieff Road junction (east side) took place this week.

Works have commenced upgrading cycle path NCR77 along the bank of the River Almond, by the new bridge.

The green screen acoustic fence to the east side of the Crematorium has been completed. Work will now commence on the timber acoustic barrier to the south of this.

Works to lay the type 1 sub base to the new northbound merge slip road has been ongoing this week.

Kerbing works are ongoing on the new west connector road.