Category Archives: What’s Happening on Site

Kerbing and footpath works have been continuing on the Loop Road off the A85 Crieff Road, in preparation for surfacing works here next week. Works are also underway constucting the footpath from the new road down to the lade-side path. Works are ongoing constructing the new junction of the West Connector and A85 Crieff Road…. Read More

Another project milestone was reached this week with the opening of the new pedestrian and cyclist footbridge over the A9. The new bridge, which has been named “Inveralmond Skywalk” by a pupil at Ruthvenfield Primary School, links Inveralmond Industrial Estate with Auld Bond Road as well as linking the Town Lade path. Elsewhere on site,… Read More

Work has continued on the new footbridge over the A9 this week ready for the opening on Monday 29 October 2018. Fencing, lighting, verging and landscaping works have been taking place here. Work has commenced on the construction of the last section of the A85 West junction where the West Connector road meets the existing… Read More

Another project milestone has been reached this week with the opening of the new southbound merge slip road on to the A9. Surfacing, landscaping, road marking and signing works have been carried out here over the course of this week, ready for the road opening on Friday 19 October. Elsewhere on site, surfacing works have… Read More

Works to surface the new lade side footpath and approaches to the new footbridge over the A9 were completed this week. Landscaping and street lighting works are now taking place here. Kerbing and surfacing works have been taking place on the new access loop road off the A85 Crieff Road. Works to complete the new… Read More

Surfacing works have recommenced this week on the Ruthvenfield Link road. Works to install the footpaths linking in to the new footbridge over the A9 have been ongoing this week. Landscaping works have been ongoing to the SUDS ponds. Verge and drainage works have been taking place on the new southbound merge slip road to… Read More

Works to construct the new lade side footpath have been progressing this week laying sub-base and installing drainage. The first layer of surfacing has been laid on the Ruthvenfield link road. Kerbing works to form the footpath have also been ongoing here this week. Landscaping works have been continuing throughout the site. Street lighting and… Read More

This week has seen the southbound merge slip road on to the A9 surfaced. Work has been ongoing installing the CCTV poles.   Kerbing, safety fencing and soiling to the verge at the old A9 northbound merge slip road. Sub-base has been installed on ruthvenfield link road. Footpath works to new foot bridge approached are… Read More

This week saw the opening of the west connector road and the southbound merge slip road on to the A9. Sub-base is being installed on the new Ruthvenfield Link Road. Base course is being installed on the new southbound merge slip road on to the A9. Work has started installing the CCTV poles. Welding works are… Read More

Works have continued constructing the new parking bays on the loop road off the A85 Crieff Road. Work has been completed installing the new CCTV camera bases. Type 1 is currently being installed on the new southbound merge slip road on to the A9. Signing and barrier installation has been ongoing on the west connector… Read More