Category Archives: What’s Happening on Site

Works are continuing constructing the SUDS pond by the Crematorium. The pond bed has been completed this week with work starting on forming the footpath that will link to Allison Crescent and Pullar Terrace. Road surfacing works have been completed across S01 (new bridge over the A9), the West Connector road and the new northbound… Read More

Following the opening of the new southbound slip road off the A9 last week, work is now underway to remove the old slip. The now redundant carriageway has been removed and a new kerb line installed along the edge of the A9. Works are continuing on forming SUDS pond 1 by the Crematorium. Works to… Read More

Two major milestones were reached on the project this week with the opening of the Bertha Park link road from Inveralmond, and the southbound diverge slip road from the A9. Members of the site team attended a visit to the steel fabricators and paint shop to check on the progress of the the new footbridge… Read More

Works are progressing backfilling over SO4b pedestrian culvert. New noise attenuation fencing has been installed at Double Dykes. Kerbing works on the new footpath on the West Connector Road are progressing. Surfacing works are taking place at the junction of SO1 over bridge and the southbound off slip road. Footway works at junction.   Lining works taking… Read More

Works are progressing forming the new SUDS pond by the Crematorium. Road surfacing works have been taking place on the new A9 northbound merge slip road, across the new bridge over the A9 and to the West Connector road this week. Safety barrier installation has been taking place on the new A9 southbound diverge slip… Read More

Works on the new footway and cycleway links to National Cycle Route 77 in the Ruthvenfield area were completed this week and the new path open to the public. The formation of the SUDS pond has also been completed with planting and landscape works still to take place here in the coming weeks. Expansion joints… Read More

Surfacing works were completed on the new A85 east tie in this week which has allowed the removal of the temporary traffic signals in this area a week earlier than originally programmed. Works in this area are now focusing on construction of the loop road. Base and binder course surfacing works have also been ongoing… Read More

The surface course of the new southbound diverge was laid this week, completing the surfacing works on this section. Works are ongoing on the new A85 east junction, installing the new kerb line, surfacing the footpaths and installing lighting, utility ducts and drainage. Road markings have been laid to the section of road leading to… Read More

Works to surface the southbound diverge have commenced this week. The base and binder road surface courses have been laid with the final course due to be laid next week. Works have continued on the A85 east junction tie in with kerbing and footpath construction works ongoing here. The installation of the acoustic fence has… Read More

Surfacing works to tie in the new A85 Crieff Road junction (east side) took place this week. Works have commenced upgrading cycle path NCR77 along the bank of the River Almond, by the new bridge. The green screen acoustic fence to the east side of the Crematorium has been completed. Work will now commence on… Read More