Category Archives: Scotland

Please click here to view presentation given to CIHT members on 25 February 2020 in AK Bell Library, Perth.

Work to install the temporary bridge across the River Almond is nearing completion with the final push of the bridge taking place last week. A video of this can be viewed on @PTFutures1 twitter feed. Final preparations are being made to this structure with an aim to it opening to site traffic in the new… Read More

This week has seen tree felling and site clearance works continue to the East of the A9, with works also continuing on construction of the haul road through the site and around the Bertha Park area. Specialist instrumentation is currently being installed to monitor the ground in preparation for the earthwork construction which is due… Read More

The first month of this project has seen enabling works carried out which has included tree felling around the A9 and River Almond areas, extensive topsoil stripping, formation of the haul road through the site and preparations for commencing the construction of the embankments.   This week has also seen the arrival of the temporary… Read More

Work on the construction of the Phase 1 of the Perth Transport Futures Project started in late September 2016. The works will take around 2½ years to complete with the estimated completion date in March 2019.