All posts by admin

What’s happening on site 14-12-2018

Works to remove the redundant slip roads have taken place this week, with the old road surface planed out and removed, and soiled over. This will be planted up in the coming weeks.

Landscaping works have been taking place along the Crieff Road, where footway surfacing works has also been completed this week.

New road signs and traffic signals have been installed at the Crieff Road junctions.

Work has been continuing finishing off the new pedestrian underpass by the lade.

What’s happening on site 30-11-2018

Works to complete the remaining footpath and kerbing works at the A85 east junction by Tulloch Terrace have been ongoing this week and are now nearing completion with only the road and footway surfacing still to complete.

Surfacing has been completed to the footpaths on Ruthvenfield Link road.

Work is ongoing completing the new lade side pedestrian underpass.

Road signing and street lighting works have been continuing throughout site this week.

Works to complete the A85 west junction have been continuing this week.

What’s happening on site 23-11-2018

Road and footway surfacing works have been taking place this week on the new loop road off the A85 Crieff Road.

Surfacing works have also been ongoing this week at the new A85 Crieff Road junction with the West Connector.

Signing and street lighting works have been ongoing throughout the site.

Drainage works have been taking place adjacent to the new northbound merge slip road.

Landscaping works have been continuing on the new ladeside path.

What’s happening on site 16-11-2018

Works are continuing constructing the new loop road off the A85. Kerbing, surfacing and landscaping works have been ongoing here this week.

Traffic signal infrastructure is currently being installed to complete the new A85 West Junction with the West Connector road.

The construction of the path linking the new road with the lade-side path has been ongoing this week with the path formed and type 1 sub base installed.

Kerbing works are ongoing on Ruthvenfield Link road.

Street lighting and landscaping works are ongoing in various locations on site.

What’s happening on site 09-11-2018

Kerbing and footpath works have been continuing on the Loop Road off the A85 Crieff Road, in preparation for surfacing works here next week. Works are also underway constucting the footpath from the new road down to the lade-side path.

Works are ongoing constructing the new junction of the West Connector and A85 Crieff Road.

Kerbing works are taking place on the Ruthvenfield Link Road.

Street lighting and landscaping works are ongoing throughout the site.

What’s happening on site 02-11-2018

Another project milestone was reached this week with the opening of the new pedestrian and cyclist footbridge over the A9. The new bridge, which has been named “Inveralmond Skywalk” by a pupil at Ruthvenfield Primary School, links Inveralmond Industrial Estate with Auld Bond Road as well as linking the Town Lade path.

Elsewhere on site, landscaping works including tree and shrub planting are ongoing at Ruthvenfield Roundabout and the Town Lade path.

Street lighting works are ongoing at various locations throughout site.

Kerbing and road construction works are taking place on the Loop Road off the A85 Crieff Road and the new West Connector junction with the A85.